· Nothing much less compared to the last two weeks
· Still in the cable gang.
· I’m doing jointer’s job, technician’s job and also foreman’s job.
· Shutdown procedure :
1. The monthly shutdown schedule was prepared and submits to RCC (regional control center) two month before.
2. Submit the actual shutdown schedule to RCC a month before.
3. After getting an approval from RCC, they will key in the data in online shutdown management system to print out the notices for consumer.
4. Sent the notice to consumer to let them know there will be no electricity supply during this time.
5. The authorized person (AP) will request permission from controller for the shutdown process.
6. RCC will issue authorization to AP.
7. For safety, AP will issue a SKMK ( Sijil Kebenaran Melakukan Kerja ) or PTW ( Permit To Work ) to CP.
8. Started the preventive works.
9. CP (competence person) will cancel the PTW and submitted to AP.
10. AP will canceled the Autorization that given by RCC.
11. Start switching again
12. After everything was back to normal (electric supply was back again) informed RCC.
No comments:
Post a Comment